UnitsScopeCompletedBalancePhysical Progress Completed as on 23.09.2026
Maincarriageway
Earthwork up to SG TopKm42.633.858.1579.46%
GSBKm94.29231.5462.75233.45%
WMMKm92.03922.5769.46924.52%
DBMKm92.0391379.03914.12%
BCKm92.039092.0390.00%
Rigid PavementKm1.42701.4270.00%
ShouldersKm42.600042.6000.00%
Service Road
EmbankmentKm24.9024.90.00%
SGKm24.9024.90.00%
GSBKm24.9024.90.00%
WMMKm24.9024.90.00%
DBMKm24.9024.90.00%
BCKm24.9024.90.00%
KerbKm24.9024.90.00%
Retaining WallKm21.80021.800.00%
Culverts & Structures
Box Culvertsnos28171160.71%
Pipe Culvertsnos60461476.67%
Minor Bridgesnos211204.76%
Major Bridgesnos5000.00%
VUPnos101910.00%
LVUPnos770100.00%
SVUPnos1511473.33%
ROB'snos2000.00%
RUBnos1000.00%
Other Misc Work
DrainsKm240240.00%
Road FurnitureKm490490.00%
Median PlantationKm490490.00%
Toll PlazaNos2020.00%
ATMSKm490490.00%